30GXN,R153, 163, 174, 178 AND ASSOCIATED MODULAR UNITS
UNIT
30GXN,R
MAXIMUM SHIPPING
WEIGHT WITHOUT
PACKAGING
MAXIMUM SHIPPING
WEIGHT WITH
PACKAGING
LIFTING HOLES CENTER OF GRAVITY
ABCD
lb kg lb kg in. mm in. mm in. mm in. mm
153, 283A,
328B, 393B,
418B
9,446 4285 10,446 4738 82.0 2083 99.0 2515 35.0 889 106.0 2692
153, 283A,
328B, 393B,
418B
10,846 4920 11,846 5373 82.0 2083 99.0 2515 35.0 889 106.0 2692
163, 303A
10,041 4555 11,041 5008 60.0 1521 103.0 2616 37.0 940 133.0 3378
163, 303A
11,709 5311 12,709 5765 60.0 1521 103.0 2616 37.0 940 133.0 3378
174
9,476 4298 10,476 4752 82.0 2083 99.0 2515 35.0 889 106.0 2692
174
10,876 4933 11,876 5387 82.0 2083 99.0 2515 35.0 889 106.0 2692
178,
328A, 353A/B
10,122 4591 11,122 5045 60.0 1521 103.0 2616 37.0 940 133.0 3378
178,
328A, 353A/B
11,790 5348 12,790 5801 60.0 1521 103.0 2616 37.0 940 133.0 3378
LEGEND
Unit with Optional Copper-Fin Coils
NOTES:
1. 2.62 in. (67 mm) diameter holes provided for lifting unit with Schedule 40 pipe.
2. Rigging option 1:
Rig with a minimum of 25 ft (7620 mm) chains or cables.
If a central lifting point is used, it must be a minimum of 13 ft (3962 mm) above
the top of the unit.
Spreader bars made from steel or double-nailed and notched 2 x 6s approxi-
mately 8 ft (2438 mm) long must be placed just above the top of the unit and
stacks to reduce the risk of damage to the top of the unit and coil.
Chains on the cooler/compressor side must be shortened by 20 in. (508 mm),
by the use of grab hooks for a more level lift.
Two-in. diameter, schedule 40 pipes should be used in the unit rigging holes.
3. Rigging option 2:
Rig with a minimum of 12 ft (3658 mm) chains or cables.
If a central lifting point along the bar is used, the lift point must be over the
center of gravity.
Lifting bars must be a minimum of 8 ft (2438 mm) long, and must be placed
just above the top of the unit and stacks to reduce the risk of damage to the
top of the unit and coil.
Two-in. diameter, schedule 40 pipes should be used in the unit rigging
holes.
4. If overhead rigging is not available, the unit can be moved on rollers or
dragged. When unit is moved on rollers, the unit skid, if equipped, must be
removed. To lift the unit, use jacks at the rigging points. Use a minimum of
one roller every 3 ft [915 mm] to distribute the load. If the unit is to be
dragged, lift the unit as described above, and place unit on a pad. Apply
moving force to the pad, not the unit. When in its final location, raise the
unit and remove the pad.
5. Check bill of lading for shipping weight of unit.
6. Center of gravity for lifting purposes only.
All panels must be in place when rigging unit. Do not attempt to forklift
unit if no skid is supplied.
Fig. 28 — Rigging Information (cont)