Chapter 1 Install the Shelf and Common Control Cards
NTP- G18 Connect Office Power to the ONS 15454 ANSI
Warning
When installing or replacing the unit, the ground connection must always be made first and
disconnected last.
Statement 1046
Note The battery return connection is treated as DC-I, as defined in Telcordia GR-1089-CORE Issue 3.
Note If the system loses power or both TCC2/TCC2P cards are reset and the system is not provisioned to get
the time from a Network Time Protocol/Simple Network Time Protocol (NTP/SNTP) server, you must
reset the ONS 15454 clock. After powering down, the date defaults to January 1, 1970, 00:04:15. To reset
the clock, see the “NTP-G24 Set Up Name, Date, Time, and Contact Information” procedure on
page 3-10. If you are using the TCC2/TCC2P cards, the system clock will run for up to three hours. In
this case, no action would be required.
Step 1 Connect the office power according to the fuse panel engineering specifications.
Step 2 Measure and cut the cables as needed to reach the ONS 15454 from the fuse panel. Figure 1-18 shows
the ONS 15454 power terminals.
Step 3 Dress the power according to local site practice.
Figure 1-18 Cisco ONS 15454 Power Terminals
Step 4
Remove or loosen the #8 power terminal screws on the ONS 15454. To avoid confusion, label the cables
connected to the BAT1/RET1 (A) power terminals as 1 and the cables connected to the BAT2/RET2 (B)
power terminals as 2.
Onsite/Remote Onsite
Security Level None
33921
RET 1
CAUTION: Remove power from both
the BAT1 and terminal blocks
prior to servicing
SUITABLE FOR MOUNTING ON
A NON-COMBUSTIBLE SURFACE.
PLEASE REFER TO INSTALLATION
INSTRUCTIONS.
-42 V 24 A
BAT 1 RET 2 BAT 2
Battery leads (red)
Return leads (black)