9 | Electrical installation
Installer reference guide
126
EPRA08~12EAV3+W1 + ETVH12SU18+23EA6V
Daikin Altherma 3 H MT F
4P644482-1 – 2021.03
a Installation of EKRP1HBAA is required.
b Prewiring between X2M/7+9 and Q1L (=thermal protector backup heater). Do NOT
change.
3 Fix the cable with cable ties to the cable tie mountings.
9.3.8 To connect the changeover to external heat source
Wires: 2×0.75mm²
Maximum load: 0.3A, 250VAC
Minimum load: 20mA, 5VDC
[9.C] Bivalent
1 Open the following (see "7.2.5To open the indoor unit"[469]):
1 Top panel
2 User interface panel
3 Upper switch box cover
2 Connect the changeover to external heat source cable to the appropriate
terminals as shown in the illustration below.