9 | Electrical installation
Installer reference guide
128
EPRA08~12EAV3+W1 + ETVH12SU18+23EA6V
Daikin Altherma 3 H MT F
4P644482-1 – 2021.03
a Installation of EKRP1AHTA is required.
3 Fix the cable with cable ties to the cable tie mountings.
9.3.10 To connect the safety thermostat (normally closed contact)
Wires: 2×0.75mm²
Maximum length: 50m
Safety thermostat contact: 16VDC detection (voltage supplied by PCB).
The voltage-free contact shall ensure the minimum applicable load of
15VDC, 10mA.
—
1 Open the following (see "7.2.5To open the indoor unit"[469]):
1 Top panel
2 User interface panel
3 Upper switch box cover
2 Connect the safety thermostat (normally closed) cable to the appropriate
terminals as shown in the illustration below.
Note: The jumper wire (factory-mounted) must be removed from the respective
terminals.