9 | Electrical installation
Installer reference guide
120
EBLA09~16DA + EDLA09~16DA
Daikin Altherma 3 M
4P620241-1 – 2020.06
K1A Relay for Smart Grid contact 1
K2A Relay for Smart Grid contact 2
X10M Terminal block
a Screws for X10M
b Screws for K1A and K2A
c Sticker to put on the high voltage wires
d Wires between the relays and X5M (AWG22 ORG)
e Wires between the relays and X10M (AWG18 RED)
9 105 6
X5M
K1A K2A
X10M
1 2 3 4
b
b
b
b
a
a
2 Connect the low voltage wiring as follows:
S4S Smart Grid pulse meter (optional)
3 Connect the high voltage wiring as follows: