OM 1130-2 81
Maintenance Schedule
A. Performance Evaluation (Log & Analysis) *
•
X
• Ampere Balance (within 10%)
•
Terminal Check (tight connections, porcelain clean)
X
•
Motor Cooling (check temperature)
C. Lubrication System
•
• Oil Appearance (clear color, quantity)
•
Oil change if indicated by oil analysis
X
• Check Settings and Operation
•
High and Low Pressure Cutouts
C. Clean Condenser Tubes (or as required)
D. Eddycurrent Test - Tube Wall Thickness X
B. Test Water Quality X
C. Clean Evaporator Tubes (or as required)
D. Eddycurrent Test - Tube Wall thickness (or as required)
A. Performance Evaluation (Superheat Control)
VI. Compressor - Chiller Unit
A. Performance Evaluation O
• Compressor Fittings and Terminal
•
•
X
C. Vibration Isolation Test
•
•
X
A. Examine Contactors (hardware and operation) X
B. Verify Overload Setting and Trip
C. Test Electrical Connections
A. Hot Gas Bypass (verify operation)
Ke
y: O = Performed by in-house personnel X = Performed by service personnel