2.1 Installation Checklist
As a precaution, review the following checklist to ensure proper operation:
Check for any damage
Check all wiring connections
Filters are properly positioned in air intake
WARNING:
Before removing from the packaging inspect the unit for any
damage. Report any damage to the carrier and file a damage claim.
2.2 Room Considerations
Precision air conditioning equipment is designed to control spaces within close
tolerances of temperature and humidity. However, the room must be built with a
proper vapor barrier. A film of polyethylene is often used on walls and ceilings. Walls
and floors must also be painted with vapor-seal paint. Failure to provide a vapor barrier
can compromise space conditions.
Introduction of outside air into the space should be minimized. Outside air in excess of
5% of the total circulated air volume can have a significant effect on the overall space
conditions and result in poor space control.
Install the units as close as possible to the largest heat load.