Blast chiller Service Manual
43
Rev 07/04/2015
b) Remove the probe wires from the main control terminals.
c) Attach the wires from the replacement probe wires to the wires of the existing
probe.
d) From the controller side, pull the wire of the existing probe to route the new probe
wires correctly.
e) Attach the wires to the Main Board.
Needle Probe Latest Version (Effective June 2014)
A quick connection plug will allow easy
replacement of the needle probe. The
connector is 2 poles and is only used with
NTC single core needle. Touch screen
Blast Chiller are not equipped with this
quick connector as of today.