Check the inside of combustion chamber
for foreign substances, and carefully
mount the cylinder head assembly in the
block by aligning the dowel pin with the
dowel pin hole.
Caution :
Be careful not to damage the cylinder
head gasket. If the dowel pin is not in
alignment, lift the cylinder head again
and then remount it.
After tightening the cylinder head bolts,
even at disassembling, the cylinder head
gasket should be changed a new one.
Coat the cylinder head bolts with engine
oil, and tighten in proper sequence to the
specified torque according to bolt
tightening order. (refer to the figure.).
<Cylinder Head Bolts>
However, before tightening bolts, the side parallel degree between cylinder heads should
be adjusted.
<Tightening order of bolts by steps>
(1) First stage : Coat the bolts with engine oil.
(2) Second stage : Tighten 1 ~ 2 threads with hands.
(3) Third stage : Tighten at about 6 kg
.
m with a wrench.
(4) Fourth stage : Tighten at rotating angle method 180
˚
with a wrench.
(5) Fifth stage : Finally, tighten at rotating angle method 150
˚
with a torque wrench .
However, all bolts are tightened simultaneously by above steps.
Coat the push rod with engine oil and insert it into the push rod hole.
Adjust the valve clearance as following guide.
- 114 -
EA9M3022
418 6
5 3 2 7
418 6
5 3 2 7
418 6
5 3 2 7
EDM2097I
Type 1 Type 2
Specification
M14x1.5x146 M14x1.5x150
Torque 24.5 kg
.
m
6 kg
.
m +180°+150°
(Angle torque)