- 127 -
LP Engine G430(3.0L) Base Engine Service Procedure
Valve Train Components Inspect
(Cylinder Head)
Inspect the following areas:
The valve rocker arms and ball at the mating surfaces.
These surfaces should be smooth and free of scoring
or other damage.
The valve pushrod sockets and valve stem mating
surfaces. These surfaces should be smooth with to
scoring or exceptional wear.
• The valve pushrods for bends or scored ends.
Valve Lifter Removal
Tools Required
• J 3049 Valve Lifter Remover (Plier Type)
J 9290-01 Valve Lifter Remover (Slide Hammer
Type)
1. Use the J 3049 in order to remove the valve lifters.
2. If the valve lifters cannot be removed with the J
3049 use the J 9290-01 in order to remove the
valve lifters.
VE026-3L
VE025-3L
VE024-3L

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Doosan GC25P-3 and is the answer not in the manual?

Doosan GC25P-3 Specifications

General IconGeneral
BrandDoosan
ModelGC25P-3
CategoryEngine
LanguageEnglish

Related product manuals