Inspection and Startup Checklist
25
3.0 INSPECTION AND STARTUP CHECKLIST
3.1 Inspection
___ 1. Confirm that the exterior of unit is undamaged (including cables and receptacles, if
furnished).
___ 2. Confirm that service and ventilation clearances are adequate. (See Figures 1 through 3.)
___ 3. Remove accessible exterior and internal panels.
___ 4. Inspect all wire and conductor insulation for damage.
___ 5. Check all transformer terminal connections for tightness. Retorque if necessary.
___ 6. Check all breaker connections for tightness. Retorque if necessary.
___ 7. Check all terminal block connections for tightness. Retorque if necessary.
___ 8. Check transformer mounting bolts for tightness. Retorque if necessary.
___ 9. Remove any foreign objects from the components or the interior area of the unit.
Make sure air passages on transformers are clear and free of debris.
___ 10. Check that the intake and exhaust air screens are clean and free of obstructions.
___ 11. Replace internal and exterior side panels, leaving access to circuit breakers for the following
start-up procedure.
Unit Serial Number
Unit Model Number
Date
!
WARNING
All equipment inspection procedures are to be performed with power to the unit turned off
and locked out.

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Emerson Liebert FPC and is the answer not in the manual?

Emerson Liebert FPC Specifications

General IconGeneral
BrandEmerson
ModelLiebert FPC
CategoryUPS
LanguageEnglish

Related product manuals