Envoy Installation and Operation
2013 Enphase Energy Inc. 141-00011 Rev 05
42
The Apply Profile screen appears. This screen shows the Grid Profile Status for each
microinverter. Initially the status for each unit is shown as un-set, soon followed by a status of
"propagating." After approximately 10 minutes, the status is "set."
This screen also allows you to generate a report to confirm that the microinverters have been
set with an updated grid profile.
15. Click View Device Profile Report.
The Device Profile Report screen appears.
16. Enter the site information in the window provided.