Section D - Installing the current transformers
Consumption CT installation
in grid-forming systems
Consumption CTs are installed inside the IQSystemController3/3G
for grid-forming systems.
Clamp the red and black C1 CT on the load center feed wire Line 1
(matching the IQGateway’s “L1” voltage terminal) with the CT arrow
pointing toward the load (away from the grid).
Clamp the purple and brown C2 CT on the load center feed wire
Line 2 (matching the IQGateway’s “L2” voltage terminal) with the
CT arrow pointing toward the load (away from the grid).
Risk of electrocution and equipment damage! Do not install CTs when
current is owing in the sensed circuit. Always install CT wires in the
terminal blocks before energizing the sensed circuit.
IQ Gateway Terminal Block
Not used Relay contacts
(if needed)
CU, C, AWG MIN
MEAS CAT III
OVC III
PD, B
OVC II
N L L
P
Digital Input
1 2 3 4 NO
REF CCommon
Relay
C C C
Production Consumption
Purple
Brown
Black
Red
IQ Combiner 5/5C Quick Install Guide35

Other manuals for enphase IQ Combiner 5

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the enphase IQ Combiner 5 and is the answer not in the manual?

enphase IQ Combiner 5 Specifications

General IconGeneral
Brandenphase
ModelIQ Combiner 5
CategoryInverter
LanguageEnglish

Related product manuals