EasyManua.ls Logo

enphase IQ Combiner 5

enphase IQ Combiner 5
56 pages
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Loading...
PRODUCT SKU
IQSystemController 3/3G SC200D111C240US01, SC200G111C240US01
IQCombiner5/5C
X-IQ-AM1-240-5 or X-IQ-AM1-240-5C or
X-IQ-AM1-240-5-HDK or X-IQ-AM1-240-5C-HDK
IQBattery 5P IQBATTERY-5P-1P-NA
Microinverters IQ8 Series
1. Ensure availability of the following Enphase products, as
required, on-site to implement EPC:
2. Installation of the CTs
Based on the type of system (grid-forming or grid-tied) and the EPC feature being
enabled, the CTs may have to be installed in dierent locations on a site.
Section F - Operation
Setting up Enphase Power Control
on-site during commissioning
IQ Combiner 5/5C Quick Install Guide 44
NOTE: If the installer wants generator integration or if the
Main Panel Upgrade avoidance feature (applicable in partial
home back congurations and grid-tied PV only systems) is
enabled, the Consumption CTs need to be installed between the
IQSystemController3/3G and the main panel in order to monitor
and control the current back-fed from the IQSystemController to
the main panel. Installing the CTs at this location would impact the
Aggregate power export limiting (PEL) feature. For further details
refer CT Installation Guidelines Tech Brief.
CT TYPE QUANTITY LOCATION CONDUCTOR MEASURED DIRECTION OF ARROW
Consumption CT 2 IQSystemController
Conductor from the mains breaker to
the main panel or the utility meter
Towards the mains breaker inside
the IQSystemController 3/3G
Production CT* 1 IQCombiner5/5C L1 of all PV branch circuits
Away from the PV (towards the PV
breakers in the IQCombiner5/5C)
IQBattery CT 1 IQSystemController L2 of IQ Battery branch
Away from the IQBattery (towards the
battery lugs on the IQSystemController)
* IQCombiner5/5C has the production pre-wired in the box.

Other manuals for enphase IQ Combiner 5

Related product manuals