4. Installation
4.2 Installation of leaf supporting foundation box (fig.3)
4.1 Preliminary Checks
Proceed as instructed below:
To ensure trouble-free operation, make sure
that the gate (whether existing or yet to be
installed) are within following specifications:
max. weight of single leaf 800 Kg
max. length of single gate leaf 4 m (see
table 1)
strong and rigid leaf frame
smooth gate movement
min. clearance between bottom edge of
gate and ground as in fig. 6/a (where ‘s’ =
thickness of guide bracket)
mechanical travel stops.
If any welding or brazing has to be done on
the gate, do this before installing the
automation system.
a) Existing gate with fixed hinges
Remove the gate.
Remove the bottom hinge.
If the gate cannot be removed, place
blocks under its bottom edge to support it.
b)
Existing gate with adjustable hinges
Remove the bottom hinge.
Slacken off the top hinge.
Swing the leaf around the axis of the
top hinge (fig. 4).
c)
New gate to be installed
Fit just the top hinge. If possible use an
adjustable hinge.
Fig. 6/a
Fig. 3
Fig. 4