4.2 POSITIONING
For the positioning of the equipment, provide a minimum space of 100 cm x 100 cm necessary to facilitate
both normal activities and adjustments and maintenance.
Once the machine has been freed from its packaging, transfer it carefully bench having a minimum size of
40 cm x 40 cm, capable of supporting a weight of at least 100 kg.
4.3 PREPARATIONS FOR ENERGY SOURCES
Set up a bipolar single-phase outlet with earth ground at the work site
We accept no responsibility for accidents resulting from bad connections.
5 DIRECTIONS AND MAINTENACE
5.1 COMMANDS
The device is equipped with the following commands:
Fig. 10: Commands
1. Vibration switch (1), Fig. 10;
2. Vibration intensity adjustment knob (2), Fig. 10.
5.2 PRELIMINARY CHECKS AND SETTINGS
Before starting the machine, carry out the following checks:
Check the ignition of the machine: main switch on the inserted position and on indicator light on,
Fig. 10;
Check the exact type of capsules that you want to process with the plates mounted on the capsule
filler;