4. Commissioning
4-5
Festo P.BE-CPVSC-EN en 0112NH
4.2 Testing the valves
Please note
Before commission i ng the CPV-SC valve terminal, note the
specifications concerning the medium, see section 3.3.1
“Auxiliary pilot air” in the chapter “Installation”.
The CPV-SC valve terminal should be commissioned as fol-
lows:
Commissioning variants
Activity
Preliminary test of the pneu-
matic tubing
Testing the valve-cylinder- com-
bination by means of the manual
override
Complete commissioning of the
complete system
Installing and connecting the
complete system. Program
control via PLC/industrial PC
Commissioning the pneumatic components by means of the
manual overr ide is described below.