MODEL 3150 UP-FLOW
Job Specification Sheet
Printed in U.S.A.
* JOB NO. __________________________________________________________
* MODEL NO. _______________________________________________________
* WATER TEST______________________________________________________
* CAPACITY PER UNIT _______________________________________________
* MINERAL TANK SIZE DIA.________HEIGHT_________
* BRINE TANK SIZE & SALT
SETTING PER REGENERATION: ______________________________________
Page 2
* CONTROL VALVE SPECIFICATIONS
1) Type of Timer (see pages 19, 20, & 21)
A) 7 day or 12 day
B) * 3,750 to 63,750 gallon meter or
* 18,750 to 318,750 gallon meter or
* Other _______________________________________________________
C) Meter Wiring Package
1) System #4 - 1 tank; 1 meter; immediate or delayed regeneration
2) System #5 - 2 tanks; 2 meters; interlock
3) System #6 - 2 tanks; 1 meter; series regeneration
4) System #7 - 2 tanks; 1 meter; alternator
2) Timer Program Settings
A) Backwash __________________________ min.
B) Brine & Slow Rinse ___________________ min.
C) Rapid Rinse_________________________ min.
D) Brine Tank Refill______________________ min.
3) Drain Line Flow Controller ________________ gpm.
4) Brine Line Flow Controller ________________ gpm.
5) Injector Size # __________________________
6) Service Valve Operation Units (SVO)
Size of Service Valve ____________________.