Bend the combustion chamber seal up approx. 3-4 cm at each end
❒ Place the seal at the front of the boiler with the turned up end facing up
➥ The turned up end forms the side seal for the triangular stone
❒
Place the seal around the combustion chamber and push in with a blunt object
❒ Place the triangular stone at the front of the combustion chamber as shown
❒ Finally, fit the linking plates and combustion chamber door again
➥ Follow the above steps in the reverse order to dismantle
⇨ See "Removing the old combustion chamber" [page 5]
2
Replacing the combustion chamber
Installing the new combustion chamber