Bend the combustion chamber seal up approx. 3-4 cm at each end
Place the seal at the front of the boiler with the turned up end facing up
The turned up end forms the side seal for the triangular stone
Place the seal around the combustion chamber and push in with a blunt object
Place the triangular stone at the front of the combustion chamber as shown
Finally, fit the linking plates and combustion chamber door again
Follow the above steps in the reverse order to dismantle
⇨ See "Removing the old combustion chamber" [page 5]
2
Replacing the combustion chamber
Installing the new combustion chamber
10 Froling GesmbH | A-4710 Grieskirchen, Industriestraße 12 | www.froeling.com

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Froling FHG Turbo and is the answer not in the manual?

Froling FHG Turbo Specifications

General IconGeneral
BrandFroling
ModelFHG Turbo
CategoryBoiler
LanguageEnglish

Related product manuals