4. Connection and Settings
Connecting to the Server UPS Unit
FUJITSU Storage ETERNUS AF, ETERNUS DX Configuration Guide (Power Synchronized Unit)
Copyright 2019 FUJITSU LIMITED P3AM-8012-14ENZ0
54
Connecting the Server UPS Unit to the Power Synchronized Unit
This section describes the procedure for connecting a power synchronized unit to a server UPS unit with the power
cord (for AC sensor).
Power cords (for AC sensor) must be obtained by customers.
1 Connect the power cords (for AC sensor) to the power synchronized unit.
1-1 Connect the plugs of the power cords (for AC sensor) to SENSOR#0 port and SENSOR#1 port on the
power synchronized unit.
Do
• When connecting external (signal, power, etc.) cables, avoid placing stress on
them. Not doing so may damage the cables.
• Do not forcibly bend or fold the cable. Doing so may damage the cable and cause
the power synchronized unit to malfunction.
90
Do not bend
more than 90 degrees
Do not fold
SENSOR#0 port SENSOR#1 port
Power cord
(for AC sensor)