OPERATION EDR-SOLA-IOM-2022-0216 SECTION 3
screen for a lead lag boiler plant or through the central heat setpoint screen
for a standalone boiler. The low water temperature and the minimum and
maximum outdoor temperatures can be congured through the outdoor reset
conguration screen displayed in Figure 65.
To enable warm weather shutdown for a lead lag boiler plant start from the
boiler status screen and select congure. Scroll to and select lead lag master
conguration. Select the box labeled advanced in the bottom right hand corner.
Using the left and right arrow keys scroll to the screen labeled warm weather
shutdown. The row labeled enable needs to be set to shutdown after demand
ends.
For a standalone boiler application warm weather shutdown must be congured
through a dierent screen. This screen can be found by selecting congure
from the boiler status screen. Scroll to and select warm weather shutdown
conguration and follow similar steps as above.
FIGURE 66  OUTDOOR RESET CURVES
FIGURE 67  WARM WEATHER SHUTDOWN CONFIGURATION
! WARNING
All information in this manual is for
reference and guidance purposes,
and does not substitute for required
professional training, conduct,
and strict adherence to applicable
jurisdictional/professional codes and
regulations.
Non-Fulton product information is for
reference purposes only. No Fulton
document may substitute for full
review of documentation available
from the component manufacturer.

Related product manuals