EasyManua.ls Logo

GE SF6 User Manual

GE SF6
300 pages
To Next Page IconTo Next Page
To Next Page IconTo Next Page
Page #1 background imageLoading...
Page #1 background image
Content
Instruction Manual
GE Information04- 2017 D1736EN/03
1/10
SF
6
circuit- breaker
GL317
With spring operating mechanisms
FK3- 4
Administrator First issue Compiled by Approved by
AHT 19- 11- 2012 J. Bossu V. Texier
Imagination at work
Grid Solutions
Question and Answer IconNeed help?

Do you have a question about the GE SF6 and is the answer not in the manual?

GE SF6 Specifications

General IconGeneral
BrandGE
ModelSF6
CategoryCircuit breakers
LanguageEnglish

Summary

Introduction

Safety

Product Safety Sheets

Information on safety sheets for product compliance and safety.

Technical Data

Technical Characteristics

Details of the circuit breaker's technical specifications.

Description and Operation

General Description of the Circuit-Breaker

Overview of the circuit breaker's main components and function.

Description of the Interrupting Chambers

Details on the interrupting chambers and their components.

Pole Operation (Interrupting Principle)

Explanation of the circuit breaker pole's operational principle.

Operating Device

Description of the operating device and its functions.

SF6 Gas Monitoring

Information on monitoring the SF6 gas pressure and density.

Packaging - Shipping and Storage

Packaging - Identification - Storage

Guidelines for packaging, identifying, and storing components.

Installation

Erection General Instructions

General guidelines for environmental and erection procedures.

Tightening Torques

Specific torque values for tightening screws during assembly.

Erection General Procedures

Step-by-step procedures for proper erection.

SF6 Gas Handling Procedures

Procedures for SF6 gas handling, vacuum, filling, and pressure calculation.

Component Installation

Steps for installing key components like frames, columns, terminals, capacitors, and devices.

Lifting and Positioning the Pole

Guidelines for safely lifting and positioning the circuit breaker pole.

Commissioning

Pre-commissioning Inspections

Checks to be performed before commissioning the circuit breaker.

Commissioning Test Report

Details regarding the commissioning test report and its content.

Acceptance Criteria

Criteria to be met for acceptance of the installed circuit breaker.

Maintenance

Maintenance Plan

Overview of the planned maintenance schedule and procedures.

Electrical Wear Limits

Guidelines on electrical wear limits for components.

Electrical Contact Densimeter Threshold Inspection

Procedure for inspecting electrical contact densimeter thresholds.

Intervention on the Operating Device

Procedures for maintenance and intervention on the operating device.

Annexes

Tooling and Accessories

List of special tooling and accessories required for operations.

End of Equipment Service Life

Dismantling and Recovery of Circuit Breaker Components

Procedures for dismantling and recovering circuit breaker components.

Management of SF6 Gas

Guidelines for managing SF6 gas during equipment end-of-life.

Guidelines for Handling Used SF6 Gas and Secondary Products

Instructions for handling used SF6 gas and by-products.