Replacement Procedures
8-50 Vivid E80/E90/E95 – Service Manual
GC091052
Rev. 3
Install the Wagon, A/N Drawer Sheet Met.
Follow these steps to install the Wagon, A/N Drawer Sheet Met.
1. Fasten the ground cable (Cable, GND, A/N Drawer) to the
Wagon, A/N Drawer Sheet Met. Assy by use of screw M4x6
/ washer tooth 4.3 (both sides of cable shoe), torque:
5,7 Nm.
2. Slide the Wagon, A/N Drawer Sheet Met. Assy into the
J-Rails w/Linings.
3. Place the J-Rails / Wagon into the tracks in UI Frame,
Lower.
4. Fix the J-Rails / Wagon to the UI Frame, Lower by using 6x
screw M4x8 and washer, flat 4.3mm (7), torque: 2,3 Nm.
5. Connect the grounding cable, Cable, GND, A/N Drawer to
the UI Mtg. Fork by use of nut M6 w/lock and washer tooth
6.4 between cable shoe and UI Mtg. Fork, torque: 5.7 Nm.
6. Install the A/N Keyboard.

Table of Contents

Other manuals for GE Vivid E90

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the GE Vivid E90 and is the answer not in the manual?

GE Vivid E90 Specifications

General IconGeneral
BrandGE
ModelVivid E90
CategoryMedical Equipment
LanguageEnglish

Related product manuals