Back End Processor (BEP) parts replacement
Vivid E80/E90/E95 – Service Manual 8-103
GC091052 Rev. 3
Preparations (continued)
When preparing for the replacement, you must perform the
following steps:
1. Record the Ultrasound system’s TCPIP settings and
installed Option strings.
2. Back up the Patient Archive images, Report Archive,
User-Defined Configuration (Customer Presets), and
Service settings. You will perform a Restore after the install.
3. Reload the system software from removable media. Select
No when asked: Keep User Data and Patient Archive?
4. Power down the Ultrasound system.
5. Disconnect the Mains Power Cable from the wall outlet.
6. Disconnect all external cables (probes, ECG, physio,
Ethernet, audio, video, USB).
7. Remove the Left Side Cover.
8. Remove the BEP Cover.
Hard Disk Drive (HDD) removal procedure
Follow these steps to remove the HDD:
1. Disconnect the cables connecting the HDD.
2. Remove the two screws that secures the HDD Bracket to
the BEP’s frame.
3. Get hold of the HDD assembly and pull it out.