10 Standard Flue - Length, Preparation and Installation
10.10 Flue Fitting
IMPORTANT:-
The ue seals are sensitive to mineral oil based lubricants. Do
not grease the seals. If the seals do need to be lubricated
use only water.
During the installation of the ue system, ensure that debris
such as mortar, lings or swarf are cleared from the ue
system before completion.
Long lengths of ues must be secured to the walls or ceilings
they run against. Use at least one xing bracket for every ue
extension that is used.
After cutting inner ue tubes ensure that you de-burr and
chamfer the male tube end to prevent damage.
Inspect the ue pipes before tting and do not install damaged
or dented ue components.
When assembling the ue system, ensure that the inner
seals are not damaged, do not install a ue component with a
damaged seal.
When tting ue elbows ensure that they are tted at the
correct angle to avoid strain, this will ensure that the seal ts
correctly preventing leakage.
Remove the ue elbow.
Separate the ue duct from the terminal by twisting to release
the terminal catch, then pull out of the retaining seal, refer to
diagram 10.16.
The ue duct cutting length (L + 11mm.) is shown in diagram
10.16.
The air duct should be cut at the opposite end to the terminal
The plastic ue duct MUST be cut at the opposite end to the
terminal catch.
The plastic ue duct extensions MUST be cut at the opposite
end to seal.
Insert the ue duct into the air duct terminal assembly,
remembering to engage the catch within the terminal.
Fit the sealing collar behind the locating lugs on the ue
terminal, see diagram 10.17.
Push the ue assembly into the wall, externally or internally,
initially until the end of the assembly protrudes a short way
from the inside face of the wall. This will enable the internal
trim ring (if required) to be positioned and allow the ue
assembly to be drawn back into the ue elbow.
Secure the ue elbow in position on top of the boiler with four
torque headed screws supplied.
Draw the ue assembly from wall and engage the ue duct
into the elbow and butt t between the air duct and ue elbow.
Fit the securing collar into position.
Ensuring correct alignment of the ue, mark through two of
the pre drilled holes in the securing collar. Remove securing
collar and drill two 3mm diameter holes one in the elbow and
one in the air duct, take care not to pierce the inner ue duct.
Fit the securing collar and secure with screws provided, see
diagram 10.17.
Slide the internal trim ring back against the wall, securing in
place with a small amount of sealant if required.
NOTE: If the air and ue ducts have been correctly cut to the
instructions the sealing collar should t ush with the outside
wall.

Other manuals for Glow-worm Ultracom 24cxi

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Glow-worm Ultracom 24cxi and is the answer not in the manual?

Glow-worm Ultracom 24cxi Specifications

General IconGeneral
ManufacturerGlow-worm
ModelUltracom 24cxi
CategoryBoiler
TypeCondensing
Output24 kW
Efficiency89.3%
Fuel TypeNatural Gas
Efficiency RatingA
ERP RatingA
MountingWall Mounted
Max. Working Pressure3 bar
Warranty2 Years
FuelNatural Gas
Flow Temperature Range30°C - 80°C
Dimensions740mm x 418mm x 300mm

Related product manuals