72 Gossen Metrawatt GmbH
15.13 Testing Extension Cords for Correct Function – EL1
* No checking for reversed wires when the EL1 adapter is used
Attention!
!
This function permits an evaluation of the continuity of
the extension cord’s active conductors L(1, 2, 3) and N.
The PE conductor isn’t tested in this case.
Measurement at Single-Phase Extension Cords with EL1
Schematic Diagram
Wiring Diagram
Measurement at Single and 3-Phase Extension Cords with VL2E
Schematic Diagram
Wiring Diagram
Measurement at Single and 3-Phase Extension Cords with AT3-IIIE
Schematic Diagram
Wiring Diagram
Single Measurements, Rotary Switch Level: Green
Rotary Switch
Position
Measuring Functions Meas. Type
Without Mains
to Test Socket
EL1
Extension cord test
with adapter for single or 3-phase extension cords for
testing for:
– Continuity
– Short-circuit
– Incorrect polarity (reversed wires *)
EL1 adapter
EL1 adapter (continu-
ity only)
AT3-IIIE adapter
VL2E adapter
Testing for Continuity
L(1/2/3), N
Short-Circuit
Between:
L(1/2/3), N
Polarity
Reversal /
Clockwise
Phase Sequence
EL1 adapter
XX
EL1 adapter
(continuity only)
X—
VL2E adapter
XXX
AT3-IIIE adapter
XXX
EL1

Table of Contents