GMV5 D.C INVERTER MULTI VRF SERVICE MANUAL
244
5. Install a new heat
exchanging board.
●Screw the support of the heat
exchanging board and fix the board
onto the chassis.
●Put the heat exchanging board
based on the position of the suction
and discharge pipes and weld the
pipes with the heat exchanging
board.
●During welding, charge nitrogen
into the pipes. The pressure should
be controlled within 0.5±0.1 kgf/cm2
(relative pressure).
Note: Avoid nearby parts from being
burnt during welding.
6. Fix and wire the
electric box.
●Put the electric box back to original
position and screw it.
Connect all lines.
7. Check and install the
front panels.
●Check various parts and connecting
lines.
If no problem is found, hook the
front panels and tighten the screws.

Table of Contents

Other manuals for Gree GMV-120WM/B-F

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Gree GMV-120WM/B-F and is the answer not in the manual?

Gree GMV-120WM/B-F Specifications

General IconGeneral
BrandGree
ModelGMV-120WM/B-F
CategoryInverter
LanguageEnglish

Related product manuals