Test Operation & Troubleshooting & Maintenance 
 
1 Trial Run 
1.1 Check for Wiring 
WARNING! 
Do not check for the power supply unless proper checkout equipment has prepared and preventive 
measures have been taken, otherwise it would lead to severe injury. 
  Are sizes of connection lines and the air switch proper? 
  Does wiring comply with relative standards and electric codes? 
  Is there any incorrect wiring? 
  Does each contact work properly? 
  Is the power supply and insulation proper? 
  Are initial set points of control and protective elements satisfied? 
1.2 Check for the Water System 
  Are water inlet and outlet directions correct? 
  Is the water piping cleaned? Are there foreign matters at the pipe joints? Is the water quality 
satisfied? 
  Is insulation of water pipes in good condition? 
  Does exhaust valve of the water system work properly?   
1.3 Check for the Communication System 
When  the  unit  is  powered  on,  check  for  the  communication  system,  including:  communication 
between  AP1  and  AP2,  between  the  wired  controller  and  the  main  board.  When  there  is  unusual 
communication, this error will be displayed at the wired controller. Then, check out the cause according 
to the displayed error. See the figure below for wiring of the communication system. 
 
1.4 Trial Run 
Start  the  unit  when  there  is  no  any  problem  for  wiring  and  piping.  After  startup,  check  for  the 
electrostatic expansion valve, water pump, fan, and compressor to see if they work normally. When 
there is any error, solve it according to the troubleshooting flowchart covered in this manual. However, if 
the troubleshooting flowchart is still unhelpful, please contact GREE sales agent. 
2 Error Code List