AIR COOLED SCROLL CHILLER INSTALLATION
20
INSTALLATION
1 BEFORE INSTALLATION
1) Please check the attached documents of unit and accessories according to package list.
2) Check the model and specification according to attached documents.
3) Check the unit for damage and accessories.
4) Check the charge refrigerant for leakage.
If there is any problem, please contact the local service center.
2 INSTALLATION SITE
1) The outside place where there is enough fresh air and bearing of foundation shall also be
considered;
2) Enough space for air return and maintenance of equipments;
3) No obstacles above the unit;
4) Drainage ditch reserved for the unit;
3 CAUTIONS FOR INSTALLATION
1) Had not better install the unit in the room. If necessary, the distance between air vent and
ceiling shall at least be 3m and enough air flow volume and ventilating systems shall be
ensured.
2) Refrigerant should be non-flammable and non-toxic. Because of high density of it, the room
placing the unit must be ventilated.
3) Once leakage of refrigerant, turn off the unit immediately and contact service personnel in
time. Open fire at field is prohibited to avoid toxic gas resulted from contact of it and the
refrigerant.
4 MACHINE FOOTPRINT
Put rubber shock pad under each of the modules on the ground or the rooftop and then fix it with
bolts. Or put the units line by line on two pieces of box iron or I iron and fix with bolts. The
distance between adjacent modules should be 100 cm.

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Gree LSQWF65M/N-M and is the answer not in the manual?

Gree LSQWF65M/N-M Specifications

General IconGeneral
BrandGree
ModelLSQWF65M/N-M
CategoryChiller
LanguageEnglish

Related product manuals