GREE              Duct type Ducted Type Split Air-Conditioner Units 
76 
  CAUTION:   
① After the initial installation is finished and the main board of outdoor unit is replaced, it must 
perform debugging. Otherwise, the unit can’t operate. 
② The debugging must be performed by professional person or under the the guide of 
professional person. 
1.4 Debugging Process 
1.4.1 Confirm before Commissioning Description 
(1)  Do not disconnect the power before the installation is finished. 
(2)  All wires for controller and electric wires must be connected correctly and reliably.   
(3)  Check the fixing ring of the foot of compressor for transportaion is removed.   
(4)  Remove all sundries from the unit, such as metal chips, joint, forceps holder, and so on.   
(5)  Check whether the appearance and pipeline system are damaged during carry or 
transportation process.   
(6)  Calculate the required added refrigerant-charging volume according to the length of pipe of 
system and pre-charge the refrigerant. If refrigerant can’t be added any more when the required 
refrigerant-charging volume hasn’t been reached, record to refrigerant volume which still needs 
to be added and continue to add refrigerant during run test operation process. Please refer to 
below run test for the refrigerant-adding stage during run test process.   
(7)  After adding refrigerant, please make sure the valve for outdoor is opened completely.   
(8)  For the convenient of troubleshooting, the unit can’t be connected to the PC which installed with 
related debugging software and make sure that the data in real time of this unit can be 
inspected by this computer. Please refer to Service Manual for the installation and connection 
of the bebugging software.   
(9)  Before turn test, please do make sure that the preheat time for compressor is 8h above and 
touch the compressor to see whether preheat is normal. You can perform run test only after 
normal preheat. Otherwise, it may damage the compressor.     
1.4.2 Main Board of ODU for Debugging