20. Commissioning
20.1 Check before startup
For safety of users and unit, the unit must be started up for check before debugging. The procedures are as
below:
No. >$[@
1
If the contents of Application for Installation of this Unit by Installer are real. If not, debugging will be
refused.
2
3
No. Pre-check
1
2 Check the accessories attached with the unit for quantity, package and so on.
3 Make sure there is drawings in terms of electricity, control, design of pipeline and so on.
4 Check if installation of the unit is stable enough and there is enough space for operation and repair.
5 Completely test refrigerant pressure of each unit and perform leakage detection of the unit.
6
7
8
Are the nilometer of water tank, water temperature indicator, controller, manometer, pressure relief valve