-A34-
6 Months:or 500,000 strapping cycles
Check heating element, replace and re-adjust it if necessary.
Check strap cutter in sealing head, replace it if necessary.
Check if the connector at wiring housing to printed circuit board is firmly fixed.
Check if the safety switch on front table or right door functions well.
Make machine ready for operation. Strap one bundle manually several times, paying
attention to mal-functions, repeat procedure.
Initiating several cyclings with package manually for testing and pay attention to any
mal-functions. Make sure the strap accumulating function is well. If necessary, replace
the assistant rollers, do proper adjustments to accumulating feeding pressure or to the
clearance in the reel brake.
Slightly lubricate the sealing head (bearing points) with light lubricant if necessary.
1 year :( or 1,000,000 strapping)
Replace deflection roller if it shows visible changes.
In case of loud noise at bearings: locate them, replace the bearings.
Get machine ready for operation again, strap one bundle manually several times, paying
attention to malfunctions.