5.5 Check for leaks
To prevent the pump from running dry, the pump must be pre-filled
with liquid during initial filling.
WARNING
Discharge of dosing agent if the system is leaking
Chemical burns caused by the use of alkali, chlorine and
acid.
Carry out the initial filling of the pump with water only (with-
out chemical).
Check the leak tightness of the dosing system with water
during initial start-up.
Do not use the dosing agent until the system is tight.
During initial filling of the pump, use a separate vessel with
water.
Guide the suction pipe or suction lance into a vessel with wa-
ter.
a Make sure that the liquid level in the vessel is above
the top of the pump head.
If the pump is lead-sealed (vp), the control setting in chapter 5.5.1
can be dispensed with.