Harrington Generators International
27
498-1084 HRD060D Diesel Generator
Maintenance
Maintenance
Good maintenance is essential for safe, economical, and trouble free operation. This not only ensures that your
engine is at its optimum in fuel efciency, but maintains the engine in order to minimize the risk of breakdowns.
This will save you money in the long run, as worn items can be spotted sooner, saving further problems.
Maintenance Schedule
Service intervals will have to be reduced if the welder-generator is operated in dusty or severe conditions. The
rst service is required after 50 hours from new then as given below.
Servicing must be carried out by a competent engineer. A written record of the service work should be made
using the form contained in this manual or similar. The welder-generator must be serviced in accordance with
our recommendations for the warranty to be valid.
DO NOT use a pressure washer to clean the welder-generator as high pressure water may enter the electrical
system. Use a damp cloth or similar.
Maintenance Schedule
Daily
Checks
After the
rst 50
Hrs
Every 3
Months or
200 Hrs
Every 6
Months or
400 Hrs
Check & replenish fuel º º º º
Check & replenish engine oil º º º º
Check fuel lter for dirt and water º º º º
Check battery º º º º
Check for oil and fuel leaks º º º º
Check operation of earth leakage unit (RCD)
trip if tted.
º º º º
Check the hours run meter works º º º º
Change engine oil º º º
Clean oil lter º º º
Replace fuel lter º
Check air lter clean º
Replace air lter º
Adjust valve clearances º
Check alternator brushes & slip rings º
Check operation of MCB’s º
Control Module Safety Shut Down º
Battery Charger º
Canopy and Trolley º
General Inspections º º
Run on ¼, ½, ¾ full load for 30 minutes º º º
If you’d like to make an appointment for HGI to service your generator using our in house 26-point health