SVP LAN
por
t Description
1 Do not connect a cable to the LAN 1 port at this time. You will connect to
this port after you complete the Initial Startup wizar
d.
2 Connect the LAN 2 port to a Windows-based management console.
3 The LAN 3 port is already connected to the user LAN port on controller 1.
4 The LAN 4 port is already connected to the user LAN port on controller 2.
Step 3: Power on the storage system
Pr
ocedure
1. Conrm that the power cables on the rear panel are connected to separate PDUs,
as shown in the following gure. Then connect the PDUs to external power sources.
Note: For best pr
actice, establish power redundancy by routing the
power connections from each PDU to external power sources on
dierent branch circuits.
To prevent the storage system from being turned o by accident, make
sure the external power sources are not controlled by a wall switch.
Step 3: Power on the storage system
Installing your storage system that includes an SVP
Hitachi Virtual Storage Platform G130 (with SVP) Installation Guide 4