6.1 Verification Before Power-On
6.2 System Power-On
6.3 Battery Commissioning
6.1 Verification Before Power-On
Table 6-1 Check items and acceptance criteria
No.
Check Item
Acceptance Criteria
1
Battery installation
The installation is correct and reliable.
2
Cables routing
Cables are routed properly as required by the
customer.
3
Cable tie
Cable ties are evenly distributed and no burr
exists.
4
Grounding
The PE cable is connected correctly,
securely, and reliably.
5
Switch
The DC switch and all switches connected to
the battery are OFF.
6
Cable connection
The AC output power cable, DC input power
cable, battery cable, and signal cable are
connected correctly, securely, and reliably.
7
Unused terminal and port
Unused terminals and ports are locked by
watertight caps.
8
Installation environment
The installation space is proper, and the
installation environment is clean and tidy.

Table of Contents