7 Hoisting an RRU and Related Cables onto a Tower
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
44
2. Installation engineer B places the fiber coiler for coiling optical fibers on the fiber spools,
and installation engineer D lead the lifting sling through the stretch sling of the optical
fibers and use the other sling as a traction sling to secure the cables 4 m (13.12 ft) away
from the lifting sling, as shown in Figure 7-7.
Figure 7-7 Binding optical fibers
(1) Lifting sling
(2) Stretch sling
(3) Traction sling
Do not remove the stretch sling and protection pipe or bind optical fibers using one sling, as
shown in Figure 7-8.