2 Single UPS Commissioning
2.1 Powering On and Starting the UPS
Prerequisites
Measure the voltage and frequency values of the UPS upstream input switches.
The line voltage range is 138–485 V AC, and the frequency range is 40–70 Hz.
2.1.1 Power-On
Context
Before power-on, ensure that the devices have passed all check items in the
section "Verifying the Installation."
Before power-on, ensure that all the UPS switches and upstream switches are
OFF.
Procedure
Step 1 Turn on the upstream bypass and mains input switches.
After the UPS is powered on, initialization begins. The MDU displays the
initialization progress bar.
----End
2.1.2 Initial Startup
NO TE
Skip this section if the device is not started for the rst time.
Step 1 Set the language, date, time, network parameters, system parameters, and battery
parameters on Settings Wizard.
UPS5000-A-(30 kVA–120 kVA)
Quick Guide 2 Single UPS Commissioning
Issue 14 (2022-09-06) Copyright © Huawei Digital Power Technologies Co., Ltd. 60

Other manuals for Huawei UPS5000-A-30 kVA

Related product manuals