INSPECTION & START-UP CHECKLIST
(BASED ON UNIT CONFIGURATION, SOME CHECKLIST ITEMS MAY NOT BE APPLICABLE)
1. RECEIVING AND INSPECTION
□ Unit Received Undamaged
□ Unit Arrangement/Hand Correct
□ Unit Received Complete as Ordered
□ Unit Structural Support Complete & Correct
2. HANDLING AND INSTALLATION
□ Unit Mounted Level & Square
□ Proper Electrical Service Provided
□ Proper Service Switch/Disconnect Provided
□ Proper Access Provided For Unit & Acces-
sories
□ Proper Overcurrent Protection Provided
□ Proper Chilled Water Line Size to Unit
□ Proper Hot Water Line to Unit
□ All Services to Unit in Code Compliance
□ All Shipping Screws & Braces Removed
3. COOLING/HEATING CONNECTIONS
□ Protect Valve Package Components From
Heat
□ Connect Field Piping to Unit
□ Install Drip Pan as Required
□ Install Condensate Pan Under Piping as
Required
□ Mount, Secure, and Support Valve Packages
□ Pressure Test All Piping for Leaks
□ Insulate All Piping as Required
□ Connect Supply and Return Pipe to Correct
Coil Connections
4. DUCTWORK CONNECTIONS
□ Install Ductwork, Fittings & Grilles as Required
□
Proper Supply/Return Grille Types & Sizes
Used
□ Insulate All Ductwork as Required
5. ELECTRICAL CONNECTIONS
□ Refer to Unit Wiring Diagram
□ All Field Wiring in Code Compliance
□ Connect Incoming Power Service or Services
□ SCR Fan Speed Control Wired to Low Speed
□ Tighten All Electrical Connections Prior To
Start-Up
6. UNIT STARTUP
□ General Visual Unit & System Inspection
□ Record Ambient Temperature
□ Close All Unit Isolation Valves
□ All Ductwork & Grilles in Place
□ Start Fans, Etc.
□ Check All Ductwork & Units for Air Leaks
□ Record All Final Settings for Future Use
□ Check All Dampers for Proper Operation
□ Verify Proper Heating Operation
□ Verify Proper Cooling Operation
□ Record Electrical Supply Voltage
□ Check All Wiring for Secure Connections
□ Vent Water Systems as Required
□ All Unit Panels & Filters In Place
□ Check for Overload Condition of All Units
□ Balance Air Systems as Required
□ Check Piping & Ductwork for Vibration
□ Verify Proper Cooling Operation
□ Reinstall All Covers & Access Panels