6 Commissioning
Personnel:
n
Unit officer
6.1 Activities during commissioning
WARNING!
Danger of damage and injury due to commis-
sioning by unqualified staff!
If commissioning is performed incorrectly by
unqualified staff, serious damage to the chilled
goods can result, which in turn can seriously harm
patients.
Have all tasks performed only by staff qualified
for those tasks.
Keep unauthorised persons away from the
working area.
Commissioning consists of the following activities:
1 - Clean and disinfect the interior of the unit
Ä
Chapter 8
“Cleaning and disinfection” on page 56.
2 - Switch on the unit
Ä
Chapter 7.1 “Switching on the unit”
on page 47.
3 - Program the unit
Ä
Chapter 6.2 “Programming the unit”
on page 41.
4 - Wait until the target temperature is reached.
5 - Stock the unit
Ä
Chapter 7.5 “Stocking the unit” on page 53.
6 - Instruct the unit officer
Ä
Chapter 6.3 “Instruction and unit
handover” on page 46.
Commissioning sequence
Commissioning
Activities during commissioning
18.12.2018Refrigerator/freezer BL series40