13 Disposal
13.1 Dismantling and disposing of the pump
WARNING
Risk of injury and damage to equipment through falling and toppling parts.
► Use intact and correctly dimensioned hoisting equipment in accordance with the total weight to be
transported.
► Select the lift points for the hoisting equipment in accordance with the centre of gravity and the
weight distribution.
► Use at least two load ropes.
► Do not stand under raised loads.
Requirement:
ü Suction connection and pressure connection protected against soiling through protective cover
ü Coupling removed
1. Carefully clean the fitting surfaces of the cartridge housing3 and the outer housing4.
2. Set up the outer housing vertically and secure it against falling over.
3. Position the cartridge housing with eye bolts/hoisting equipment vertically over the outer housing.
4. Lightly grease the O-ring2.
5. Slide the cartridge pump exactly vertically into the outer housing. In the process ensure that no
seals are damaged.
6. Tighten the socket screws1 with torque.
13 Disposal
13.1 Dismantling and disposing of the pump
Personnel qualification: o Fitter
Personal protective equipment: o Work clothing
o Face protection
o Protective gloves
o Safety boots
Aids: o Solvents or industrial cleaners suitable for the pumped liquid
o Collection tank
48
OIC 18en-GB Edition 2020-01
Operating instructions