Installation and start-up of KEOR HPE UPS 60÷160 kVA
Installation et démarrage de l’ASI KEOR HPE 60÷160 kVA
Installazione e avviamento KEOR HPE UPS 60÷160 kVA
OML46086 REV. C
25
The UPS must be so installed as to ensure its serviceability and to allow a correct air flow as much
as possible.
With regard to the minimum distances from the walls, for all of the UPS sizes the same installation
conditions apply as indicated in the table below.
- UPS with internal batteries
A (mm) B (mm) C (mm) D (mm)
Recommended clearances
50 1200 600
600
Minimum clearances 0 1200 600
400
- UPS with external battery cabinet
A (mm) B (mm) C (mm) D (mm)
Recommended clearances
50 1200 400
600
Minimum clearances 0 1200 0
400
The table below shows the air volume required for an optimal ventilation and cooling of the UPS.
Power (kVA) 60 80 100 125 160
Air volume (m
3
/h) 1000 1200 1200 1500 1500