6 Commissioning of PROFIBUS
6.2 The commissioning steps in detail
28
Lenze · Controller-based Automation · PROFIBUS® Communication Manual · DMS 4.6 EN · 11/2016 · TD17
_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _
6.2.3 Create a project folder
Create a project folder on the Engineering PC.
Use this project folder to store the data generated in the following different project configuration
steps:
Project data created in the »Engineer« or »EASY Starter«
The project file created in the »PLC Designer«
Tip!
Create a separate project folder for every PROFIBUS configuration and store the project
files.
6.2.4 Commission the field devices
Parameterise the Lenze field devices connected to the PROFIBUS network by means of the
»Engineer« or »EASY Starter«.
PROFIBUS is exclusively configured using the »PLC Designer«.
PROFIBUS settings of the field devices which have possibly been carried out with the »Engineer«/
»EASY Starter« are overwritten.
Tip!
We recommend to commission each field device individually and then integrate them into
the PLC program.
Documentation of the Lenze field devices
Here you are provided with some detailed information relating to the commissioning of
the Lenze field devices.