6 Commissioning of PROFIBUS
6.2 The commissioning steps in detail
30
Lenze · Controller-based Automation · PROFIBUS® Communication Manual · DMS 4.6 EN · 11/2016 · TD17
_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _
4. Go to the Standard project dialog window and select the target system in the
Controller type selection field:
Further optional project settings
Selection of the Controller firmware version
Selection of the compiler version
Selection of the programming language:
• Sequential function chart (AS)
• Instruction list (AWL)
• Continuous Function Chart (CFC)
• Function block diagram (FUP)
• Ladder diagram (KOP)
• Structured text (ST)
5. Confirm the selection by clicking OK.