RT765E-2 OPERATOR MANUAL SAFETY INFORMATION
2
Overload less than 25%
1 Lift Cylinder Inspect for leaking.
2
Turntable
Bearing
Check bolts for proper torque.
See topic in Swing section of
Service Manual.
3 Wire Rope Inspect all for damage.
See topic in Introduction section
of Service Manual.
Overload from 25% to 49%
1 Lift Cylinder Inspect for leaking.
2
Turntable
Bearing
Check bolts for proper torque.
See topic in Swing section of
Service Manual.
3 Wire Rope Inspect all for damage.
See topic in Introduction section
of Service Manual.
4 Hoist/Drums Inspect each for damage.
5 Hoist Brakes Brakes must hold rated line pull.
6
Bearing Main
Boom Pivot
Pin
Inspect for deformation, cracked welds.
7
Lift Cylinder-
lower mount
Inspect pin and welds.
8 Turntable Inspect for deformation, cracked welds.
9 Welds Inspect for cracks.
10 Paint
Inspect for cracked paint which could indicate twisted,
stretched, or compressed members.

Table of Contents

Other manuals for Manitowoc Grove RT765E-2

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Manitowoc Grove RT765E-2 and is the answer not in the manual?

Manitowoc Grove RT765E-2 Specifications

General IconGeneral
BrandManitowoc
ModelGrove RT765E-2
CategoryConstruction Equipment
LanguageEnglish

Related product manuals