Equipment Start-up
Initial start-up of the Incremental® conditioners by
experienced personnel is usually the responsibility of the
installing contractor. This start-up consist of inspecting
and operating the equipment for all functions at the time
of initial installation and making necessary adjustments.
It also includes demonstrating its proper operation to the
owner or his agent.
Note: that unless otherwise specically agreed to in writing,
McQuay International includes no eld labor, start-up
service or the like in the price of its equipment.
After the equipment leaves the factory, it may become
damaged or maladjusted during transportation or on the
job. Sometimes wires are disconnected accidentally or
fan motors move on their bases due to rough handling,
causing fans to strike. The correction of such conditions
is part of start-up.
CAUTION
Before starting equipment, make certain that:
1. Correct voltage has been supplied to the equipment.
2. The electrical plug from the control box has been
inserted into the receptacle.
During Start-up (applies only to standard equipment):
Note: Direction of conditioner air may be adjusted by repositioning
the discharge grille(s) to change airow pattern in a room.
The building superintendent or assistant manager should be
requested to make any changes.

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the McQuay PDAC and is the answer not in the manual?

McQuay PDAC Specifications

General IconGeneral
BrandMcQuay
ModelPDAC
CategoryAir Conditioner
LanguageEnglish

Related product manuals