EasyManuals Logo

McQuay WHR 017EW User Manual

McQuay WHR 017EW
90 pages
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Page #79 background imageLoading...
Page #79 background image
Product Manual WHR-2 79
PART 3 - EXECUTION
3.01 INSTALLATION
A. Install in strict accordance with manufacturer’s requirements, shop drawings, and
Contract Documents.
B. Adjust and level chiller in alignment on supports.
C. Coordinate electrical installation with electrical contractor.
D. Coordinate controls with control contractor.
E. Provide all appurtenances required to insure a fully operational and functional
chiller.
3.02 START-UP
A. Ensure proper charge of refrigerant and oil.
B. Provide testing, and starting of machine, and instruct the Owner in its proper
operation and maintenance.

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the McQuay WHR 017EW and is the answer not in the manual?

McQuay WHR 017EW Specifications

General IconGeneral
BrandMcQuay
ModelWHR 017EW
CategoryChiller
LanguageEnglish

Related product manuals