Pellerin Milnor Corporation
B2T2001013: Hot water connection.
B2T2001014: Cold water connection.
B2T2001016: Flushing water connection. This is the water that
goes into the supply compartment or pumped chemical manifold
to flush chemicals into the machine.
B2T2006001: Remove restraints inside. Your machine requires ei-
ther one or two anchor bolts on each corner of the base, as shown.
(Not used on MCR36E4.)
B2T2006002: Remove this restraint from the vibration switch.
B2T2008007: Do not exceed 160° Fahrenheit (71° Celsius) water
temperature. Excessive temperature can damage the water valves
in this machine. Eliminate water hammer on the water lines to this
machine. Water hammer can rupture the water inlet valves on this
machine. Follow applicable codes when installing water hammer
arresters. Maintain incoming water pressure between 10 and 75
psi (between 0.7 and 5.1 bar). Pressures outside this range can
damage the water valves in this machine.
B2T2018004: Install 8 anchor bolts. Remove vibration switch re-
straint. (Only used on MCR36E4.)
End of document: BNWCAI01
Installation Tag Guidelines
19