Sequence of Operation
1. Read and follow safety precautions.
2. After installation, ensure that:
• All Reactor ground terminals are connected to ground.
• Power wiring to the utility, drive and motor is in accordance with the
interconnection diagrams supplied by the System Engineer.
3. Check that moisture has not condensed on the Reactor. If moisture is
present, do not proceed with startup until the moisture has been removed.
4. Proceed with startup according to the instructions provided by the system
supplier.
WARNING
Reactors are a component part of an electrical system. Do not proceed with startup until
the system startup instructions provided by the System Engineer are understood and
followed. Injury, death and damage to equipment may result if the system startup
instructions are not followed.
WARNING
Use extreme caution to avoid contact with line voltage when checking for
power.
INJURY OR DEATH MAY RESULT IF SAFETY PRECAUTIONS ARE
NOT OBSERVED.