– 67 –
CHAPTER 4 OFFICE DATA DESIGN
2.8.2 ACD Scheduling on a Pilot Number basis
This scheduling allows the user to assign holiday calendar and holiday schedule on a pilot number basis. Three
patterns of holiday schedule can be used.
STEP 1: ASYDL - Assign the following system data for using Holiday Schedule:
SYS 1, Index 869, Bit 1 = 1 (Holiday Schedule on a Pilot Number basis is in service).
STEP 2: ACDPLT - Assign the schedule number (1-250) to “WEEKNO” for each pilot number.
M_NO: Monitor Number
CCV/W: 0/1 = CCV/Week Schedule
WEEKNO: Schedule Number (1-250)
Example:
M_NO: 2000 M_NO:2100
CCV/W:1 CCV/W:1
WEEKNO:1 WEEKNO: 100
STEP 3: ACDWS -Assign the week schedule data.
TN: Tenant number (1-9)
SCH: Week day Schedule number (1-250) Note 1
WEEK: Day of week
MON = Monday
TUE = Tuesday
WED = Wednesday
THU = Thursday
FRI = Friday
SAT = Saturday
SUN = Sunday
HOUR, MINUTE: CCV start time Note 2
CCVNO: CCV no. (1-900)
CCVSTEP: CCV step no. (1-20)
Note: When assigning schedules, write the data after sorting.
STEP 4: ACDHCP - Assign the holiday schedule data to the month in which the schedule data is used.
WEEKNO: Schedule Number (1-250)
MONTH: Month that uses the schedule data (1-12)
DAY: Date (1-31)
SCH: Schedule Number for the holiday (0-3)
STEP 5: ACDHSP - Assign the holiday schedule data.
WEEKNO: Schedule Number (1-250)
SCH: Holiday Schedule number (1-3)
HOUR, MINUTE: CCV start time
CCVNO: CCV number (1-900)
CCVSTEP: Start CCV step number (1-20)
Note 1: The same Week day Schedule number (SCH) cannot be set to a different Tenant number (TN).